In a move to alleviate chronic traffic congestion on Mangaladevi Road, Southern Railway will install a double boom-barrier at the Pandeshwar Level Crossing to facilitate four-lane vehicular movement.

  • Double boom-barriers to be installed at an estimated cost of ₹2 crore.
  • The project aims to support four-lane traffic flow to reduce congestion on Mangaladevi Road.
  • Tenders are in the final stages, with project completion expected within six months.

The Palakkad Division of Southern Railway has announced the installation of a double boom-barrier gate at the Pandeshwar Level Crossing (LC) in Mangaluru. This strategic intervention comes as a temporary relief measure while the construction of a permanent railway over-bridge (RoB) remains pending. The upgrade is specifically designed to facilitate four-lane vehicular traffic, which is expected to significantly reduce the daily misery of commuters on the heavily congested Mangaladevi Road.

During a site inspection on September 1, 2026, Mangaluru City Corporation (MCC) Commissioner Rahul Ratnam Pandey was briefed by railway engineers that tenders for the double boom-barrier, associated civil works, and signaling and telecommunication upgrades have already been opened. The finalization of these tenders is expected within a fortnight, with the entire execution slated for completion within six months.

Why This Matters

BozokMedia analysis shows that the Pandeshwar LC gate has historically been a flashpoint for traffic gridlock due to the frequent closing of gates for trains stabling at the Bunder Yard. The transition to a four-lane compatible barrier system represents a shift toward data-driven urban management, acknowledging that single-lane barriers are obsolete for modern city traffic volumes.

Complementing the railway's efforts, Commissioner Pandey and Deputy Commissioner (Development) Naresh P. Shenoy have committed that the MCC will widen the road stretch by approximately 200 meters on both sides of the LC gate. This ensures that the increased throughput at the gate is not neutralized by bottlenecks on the approach roads.

"Infrastructure synchronization between municipal bodies and railway authorities is the only sustainable way to eliminate urban transit bottlenecks."

Regarding the long-term solution, the proposed Railway Over-Bridge (RoB) is currently under design review. While Southern Railway initially proposed a two-lane bridge, the MCC has insisted on a four-lane structure to accommodate future growth. Consequently, the Railways has requested detailed designs and drawings from the Corporation, a process that is expected to take additional time.

The project gained momentum following the persistent intervention of Dakshina Kannada MP Captain Brijesh Chowta and Mangaluru City South MLA D. Vedavyasa Kamath. Their efforts in highlighting the hardships faced by road users to the State government and Railway authorities were pivotal in securing this priority upgrade.

Did You Know?: Double boom barriers are essential for wide roads because they allow the railway to seal off multiple lanes of traffic simultaneously, preventing vehicles from attempting dangerous U-turns or bypassing the gate.

Proposed Solutions: Comparison

FeatureDouble Boom Barrier (Immediate)Railway Over-Bridge (Long-term)
Estimated Cost₹2 CroreHigh Investment
Timeline~6 MonthsMultiple Years
Traffic ImpactReduced CongestionComplete Elimination of Gridlock
Lane Capacity4 Lanes4 Lanes (Proposed)

Frequently Asked Questions

Q1: How will the double boom barrier help reduce traffic?
A: It allows four lanes of traffic to move simultaneously once the gate opens, preventing the bottleneck effect seen with single-barrier systems.

Q2: Why is the Railway Over-Bridge (RoB) delayed?
A: There is an ongoing negotiation between the Railways (who proposed 2 lanes) and the MCC (who demand 4 lanes), requiring new detailed designs.